(Solved):Jobs arrive to a two-station serial line at a rate of 2 jobs per hour with deterministic inter-arrival times. Station 1 has one machine, which requires exactly 29 minutes to process a job. Station… View Answer…

 

Question

Jobs arrive to a two-station serial line at a rate of 2 jobs per hour with deterministic inter-arrival times. Station 1 has one machine, which requires exactly 29 minutes to process a job. Station 2 has one machine which requires exactly 26 minutes to process a job, provided it is up, but is subject to failures where the mean time to failure is 10 hours and the mean time to